In August 2015 a 200-year monsoon event occurred in Northern Arizona on US 89A. The rainfall was between 1.3-1.7 inches within a 15 minute period, overwhelming drainage structures. Boulders over 15 feet in diameter smashed onto the highway. Crews arrived within 15 minutes to assess the damage. Arizona DOT has a state funding limit on emergency projects. The damage and cleanup were beyond the $700,000 limit, so they had to access FHWA Emergency Relief funding. Despite all the challenges, clean-up and repair happened in record time. Explore how they used job order contracting to accomplish this feat. Learning Objectives: Implement key best practices to better manage an emergency situation due to weather elements. Maximize resources during an emergency situation. Recognize situations ideal for the job order contracting procurement method.